Mining truck scheduling with stochastic maintenance cost 被引量:4

Mining truck scheduling with stochastic maintenance cost
下载PDF
导出
摘要 Open pit mining operations utilize large scale and expensive equipment. For the mines implementing shovel and truck operation system, trucks constitute a large portion of these equipment and are used for hauling the mined materials. In order to have sustainable and viable operation, these equipment need to be utilized efficiently with minimum operating cost. Maintenance cost is a significant proportion of the overall operating costs. The maintenance cost of a truck changes non-linearly depending on the type, age and truck types. A new approach based on stochastic integer programming (SIP) techniques is used for annually scheduling a fixed fleet of mining trucks in a given operation, over the life of mine (multi-year time horizon) to minimize maintenance cost. The maintenance cost data in mining usually has uncertainty caused from the variability of the operational conditions at mines. To estimate the cost, usually historic data from different operations for new mines, and/or the historic data at the operating mines are used. However, maintenance cost varies depending on road conditions, age of equipment and many other local conditions at an operation. Traditional models aim to estimate the maintenance cost as a deterministic single value and financial evaluations are based on the estimated value. However, it does not provide a confidence on the estimate. The proposed model in this study assumes the truck maintenance cost is a stochastic parameter due to the significant level of uncertainty in the data and schedules the available fleet to meet the annual production targets. The scheduling has been performed by applying both the proposed stochastic and deterministic approaches. The approach provides a distribution for the maintenance cost of the optimized equipment schedule minimizing the cost.
出处 《Journal of Coal Science & Engineering(China)》 2012年第3期313-319,共7页 煤炭学报(英文版)
关键词 mining truck scheduling mixed integer programming minimizing stochastic cost mining equipment 维护成本 卡车调度 随机参数 矿用卡车 操作条件 露天开采 经营成本 不确定性
  • 相关文献

参考文献26

  • 1Alarie S, Gamache M, 2002. Overview of solution strategies used in truck dispatching systems for open pit mines. In- ternational Journal of Mining, Reclamation and Envi- ronment, 16(1): 59- 76.
  • 2Alford C, 1995. Optimisation in underground mine design. //Proc. of XXV APCOM Symp (McKee Ded.). Mel- bourne: Inst. of Mining and Metallurgy. 213 -218.
  • 3Chanda E K, Ricciardone J, 2002. Long term production sched- uling optimization for a surface mining operation: an ap- plication of MINEMAX scheduling software. Interna- tional Journal of Surf&ce Mining, Reclamation and Envi- ronment, 16: 144-158.
  • 4Dodin B, Elimam A A, 2008. Integration of equipment planning and project scheduling. European Journal of Operational Research, 184: 962-980.
  • 5Ercelebi N, Bascetin A, 2009. Optimization of shovel-truck system for surface mining. South African Institute of Min- in~ and Metallurgy Journal, 109: 433-439.
  • 6Ernst A T, Jiang H, Krishnamoorthy M, Sier D, 2004. Staff scheduling and Rostering: A review of applications, methods, and models. European Journal of Operational Research, 153: 3-27.
  • 7Gershon M, 1987. Heuristic approaches for mine planning and production scheduling. Geotechnical And Geological En- gineering Journal, 5(1): 1 -1 3.
  • 8Godon L, Erkut E, 2004. Improving volunteer scheduling for the Edmonton Folk Festival. Interfaces, 34(5): 367- 376.
  • 9Godoy M, Dimitrakopoulos R, 2004. Managing risk and waste mining in long-term production scheduling. SME Trans- actions, 316: 43-50.
  • 10Groeneveld B, Topal E, 2011. Flexible open-pit mine design under uncertainty. Journal of Mining Science, 47(2): 212-226.