控制注入/压降试井测试时间因素分析 被引量:6

Analysis of Controlling Test Time in Injection/Fall off Test
下载PDF
导出
摘要 为了减少注入/压降试井对整个煤层气井施工进度的影响,基于对煤层气注入/压降试井测试理论及实际操作的研究,提出控制试井测试时间长短的几个因素,应用实例说明其解决方案,结果表明在煤层气井况、设备等基本固定的情况下,对于中高渗煤层,通过提高地面注入压力增大注入量是缩短试井测试时间的重要手段。 In order to reduce the impact of the injection/drawdown well test to the whole construction progress of the CBM wells, based on theoretical and practical research of the coal-bed methane injection/down well test, several factors to long or short of testing time for controlled wells are proposed. The applied example indicates its solutions, and the results show that under the basic fixed conditions of coal-bed methane well conditions and equipment, to meddle or high permeability CBM, injection pressure in and other basic fixed for hypertonic seam, it is an important means to shorten the time of well test by raising the surface injection volume.
出处 《油气井测试》 2012年第5期29-31,76,共3页 Well Testing
关键词 中高渗煤层 地面注入压力 实时注入量 meddle or high permeability CBM,surface injection pressure,injection volume in real time
  • 相关文献

参考文献5

二级参考文献15

  • 1庄惠农,韩永新.煤层气层渗流与煤层气试井[J].重庆大学学报(自然科学版),2000,23(z1):18-21. 被引量:18
  • 2王德山,聂立新,李兆敏.试井曲线自动拟合方法研究[J].石油大学学报(自然科学版),2005,29(2):57-60. 被引量:6
  • 3刘能强.调查半径的新定义[J].油气井测试,2006,15(4):42-43. 被引量:8
  • 4梁志军,廖新维,李祥,邵龙义.煤层气不稳定试井及其应用[J].油气井测试,2007,16(2):8-11. 被引量:4
  • 5BOURDETD.现代试井解释模型及应用[M].北京:石油工业出版社,2007.
  • 6陈志胜,王彦龙,解光新,等.GB/T24504-2009煤层气井注入/压降试井技术规范[s].北京:中国标准出版社,2010.
  • 7李彬刚.注入压降试井中注入时间的确定[G]//董书宁,张群.安全高效煤矿地质保障技术及应用学术年会文集.北京:煤炭工业出版社,2007.
  • 8杨新辉.影响煤层气井注入/压降试井测试成功率的主要因素.中国青年科技,2008,.
  • 9GB/T24504-2009.煤层气井注入/压降试井技术规范[S].
  • 10Bourdet,D.现代试井解释模型及应用[M].北京:石油工业出版社,2007.

共引文献44

同被引文献30

引证文献6

二级引证文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部