摘要
结合某工程DDC地基处理施工组织方案,详细探讨了主要工序和特殊工序的施工方法,并介绍了项目工期要求及施工进度计划,在质量保证体系的组织机构管理下,达到了单位、分部、分项工程合格率达100%,创优质工程的目标。
Combining with the construction organization scheme for the treatment for DDC foundation of some project, the paper explores the main procedure and the construction methods for the special procedure in detail, introduces the requirements for the construction period of the program and its plan for the construction progress, and indicates it achieves the acceptability of the construction party, the branches and the subdivisions 100 percent, and creates the excellent engineering aims.
出处
《山西建筑》
2013年第7期73-74,共2页
Shanxi Architecture
关键词
DDC地基处理
施工组织
施工工艺
施工方案
DDC foundation treatment
construction organization
construction craft
construction scheme