摘要
以500 kt/a催化汽油选择性加氢脱硫装置循环氢压缩机为例,全面系统地分析了往复式压缩机在安装过程中问题的处理以及各部位数据的测量与控制、调试过程中的控制要点、以及试运过程的注意事项,从而达到顺利完成缩短安装工期的目的,以期为同类型压缩机安装提供一些借鉴。
Exampled with cycle hydrogen compressor used in 500 kt/a hydrogenation de-sulfa plant, the treatment for the problems occurred in the installation of reciprocating compressor, the measurement and control of the data from various parts, the key control points in adjustment and the notes in operation were overall analyzed. It is hoped that the installation period can be shortened. What presented herein can be referenced in installation of the same machines.
出处
《化工设备与管道》
CAS
2013年第1期49-52,共4页
Process Equipment & Piping
关键词
往复式压缩机
安装
试车
reciprocating compressor
assembly
test run