高层建筑静压预应力管桩施工初探 被引量:3

About static pressing prestressed pipe pile construction technology in high-rise buildings
下载PDF
导出
摘要 对高层桩基采用静力压桩法,依据地质状况、场地条件、最大压桩力、单桩极限承载力、入土深度、桩身强度、打桩顺序、用电量平衡、引孔压桩法等,并结合当地经验综合施工。静载效果分析极限承载力比最终压桩力提高了44%~79%。与钻孔灌注桩经济对比,大吨位管桩节省造价14%。 The method of static pressing pile in high-rise building is related to geological condition, site condition, maximum pressing force, ultimate bearing capacity of single pile, buried depth, strength of pile, piling sequence, energy balance, method of pressing pile with pre-augering and local experience. According to the static loading test, the ultimate bearing capacity of single pile is increased by 44%-79% than the final pressing pile force. Compared to the bored pile, large tonnage prestressed pipe piles reduces investment about 14%.
出处 《浙江科技学院学报》 CAS 2013年第1期42-46,共5页 Journal of Zhejiang University of Science and Technology
关键词 静力压桩法 引孔压桩法 高层建筑 场地条件 最大压桩力 method of static pressing pile: method of pressing pile with pre-augering: high-risebuilding: site condition: maximum pressing pile force
  • 相关文献

参考文献6

  • 1信息产业部电子综合勘察研究院.岩土工程勘察报告书[R].2011.
  • 2中华人民共和国住房和城乡建设部.静压桩施工技术规程(征求意见稿)[S].
  • 3中华人民共和国住房和城乡建设部.JGJ94-2008建筑桩基技术规范[S].北京:中国建筑工业出版社,2008.
  • 4广东省住房和城乡建设厅.静压预制混凝土桩基础技术规程(征求意见稿)[S].
  • 5王离.静压管桩具有广阔的发展空间[J].混凝土世界,2011(1):24-26. 被引量:1
  • 6浙江煤炭测绘院.单桩竖向抗压静载荷试验报告[R].2012.

共引文献2

同被引文献12

引证文献3

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部