摘要 由于集装箱门式起重机移动速度和操作较慢,良好的调度方案显得尤为重要,针对集装箱港口进口箱,考虑从船上卸下堆存在堆场的集装箱对于起重机调度的需求,实际中同一个目的港的集装箱大都在同一个区块,因此考虑集装箱组具有实际意义。文中建立了一个整数规划模型来解决这个问题,最后通过一组算例对模型的有效性和科学性进行了分析。 Due to slow movement and operation of container gantry cranes,it's important to provide an excellent crane scheduling scheme.Considering the import containers in the container port,it's considered to unload the container group onto the corresponding yard from ships.As a matter of fact,containers in the same destination port are generally in the same block,so consideration of the container group is applicable.An integer programming model is built in the paper to solve the problem,with further analysis of effectiveness and scientification of the model by an example.
出处 《起重运输机械》 2013年第3期63-66,共4页 Hoisting and Conveying Machinery
基金 国家自然基金(71071093) 上海市自然基金(10ZR1413300) 上海市教委创新基金(11YZ136) 上海市科委创新项目(09DZ2250400 9530708200 10190502500) 上海市重点学科(J50604)
关键词 港口 集装箱门式起重机调度 集装箱组 port scheduling of container gantry crane container group
  • 相关文献

参考文献10

  • 1He Junliang, Chang Daofang, brid parallel genetic algorithm [ J ]. Transportation Research 136 - 155. Mi Weijian, et al. A hy- for yard crane scheduling : Part E, 2010 (46):.
  • 2Kim K Y, Kim K H. A routing algorithm for a single trans- fer crane to load export containers onto a container ship [J]. Computers & Industrial Engineering, 1997 (33): 673 - 676.
  • 3Kim K H, Kim K Y. An optimal routing algorithm for a transfer crane in port container terminals [ J ]. Transporta- tion Science, 1999 (33)- 17-33.
  • 4KIM K Y, Kim KH. Heuristic algorithm for routing yard- side equipment for minimizing loading times in container terminals [ J ].Naval Research Logistics, 2003 ( 50 ) : 498 - 514.
  • 5Zhang Chuqian, Wan Yat-wah, Liu Jiyin, et al. Dynamic crane deployment in eontainer storage yards [ J ]. Transpor- tation Research : Part B, 2002 (36) : 537 -555.
  • 6Ng W C. Crane scheduling in container yards with inter- crane interference [ J ]. European Journal of Operational Research, 2005, 164 : 64-78.
  • 7Lee Der-Horng, Cao Zhi, Meng Qiang. Scheduling of two- transtainer systems for loading outbound containers in port container terminals with simulated annealing algorithm[ J ]. International Journal of Production Economics, 2007, 107 (1): 115-124.
  • 8Chang D, Jiang Z, Yan W, et al. Developing a Dynamic Rolling-horizon Decision Strategy for Yard Crane Schedu- ling [ J]. Advanced Engineering Informatics, 2011, 25 ( 3 ) : 485 - 494.
  • 9Li Wenkai, Goh Mark, Wu Yong, et al. Discrete time model and algorithms for container yard crane scheduling [ J]. European Journal of Operational Research, 2010, 198 : 165 - 172.
  • 10Li Wenkai, Goh Mark, Wu Yong, et al. A continuous time model for multiple yard crane scheduling with last minute job arrivals [ J ]. International Journal of Produc- tion Economics, 2012, 136:332 - 343.