摘要
佛山市三水区北江水厂设计总规模为80×104m3/d,分三期实施,首期工程规模为30×104m3/d,采用北江地表水水源,原水经过预臭氧、絮凝反应、混凝沉淀、过滤及氯胺消毒后,出厂水水质优于爯生活饮用水卫生标准爲(GB 5749—2006).介绍了该水厂水源选择、取水构筑物工程设计、处理工艺流程以及主要处理构筑物设计参数,对该水厂的设计方案及工程特点进行了简要总结.
The total design capacity of the Beijiang Water Treatment Plant in Sanshui district of Foshan is 80 ×10^4m^3/d. The plant is divided three building periods, in which the first-phase project ca-pacity is 30 ×10^4m^3/d. The raw water which is from the north river surface water is treated by ozone pre-treatment, flocculation reaction, coagulation sedimentation, filtration and chloramine disinfection. The finished water quality is higher than the requirements in the Standards for Drinking Water Quality ( GB 5749 - 2006). The selection of water source, design of intake structure, water treatment process and de-sign parameters of main treatment units were introduced. The design plan and the project characteristics of the water plant were summarized.
出处
《中国给水排水》
CAS
CSCD
北大核心
2013年第10期35-39,共5页
China Water & Wastewater
关键词
给水厂设计
取水工程
工艺流程
water treatment plant design
intake works
process flow