净收益最大化的时间-费用交换问题研究 被引量:8

Time-cost trade-off to maximize net income
下载PDF
导出
摘要 有关时间—费用交换问题的研究主要集中在对活动的时间—费用函数关系类型与求解方法的讨论上 ,而没有考虑收入与资源对决策的影响 .本文讨论了当收入与项目进程中里程碑的实现时间相关时的时间—费用交换问题 ,提出了以净收益最大化为目标的优化模型 ,并设计了 3种利用不同新解生成机制的模拟退火过程 .通过对一个实例的对比计算说明了该模型的有效性 .同时还利用随机产生的 6 0个实例对 3种模拟退火过程的性能进行了测试 . Research on the time cost trade off problem is primarily focused on types of time cost function of each activity and algorithms. The influence of income and resource on decision was largely ignored. In this paper, a time cost trade off problem with time dependent income is presented. An optimal model is proposed to maximize net income and three simulated annealing procedures using different new solution generation mechanisms are designed for the model. A comparative calculation on an example indicates the effectiveness of the model. Furthermore, 60 activity network instances are generated randomly to test and compare the performance of the three simulated annealing procedures.
出处 《系统工程学报》 CSCD 2000年第3期267-271,276,共6页 Journal of Systems Engineering
关键词 项目管理 网络计划技术 时间-费用交换 净收益 project management network planning technique time cost trade off simulated annealing
  • 相关文献

参考文献3

  • 1康立山.非数值并行算法(第一册)-模拟退火算法[M].北京:科学出版社,1997.4.
  • 2康立山,非数值并行计算.1.模拟退火算法,1997年
  • 3冯允成,活动网络分析,1991年

共引文献6

同被引文献57

引证文献8

二级引证文献34

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部