期刊文献+

乌兹别克斯坦AmuzangⅡ主泵站技术改造

Electrical Design of Technological Transformation of the Uzbekistan Amuzang Ⅱ Main Pumping Station
下载PDF
导出
摘要 乌兹别克斯坦AmuzangⅡ泵站为大流量、高扬程的大型泵站,属于亚洲开发银行国际招标项目。该工程单机容量及总容量国内均无先例。电气设计中,既要根据工程实际情况优化选择电气主接线和配备电气设备,又要注意国外设备与国内产品配套存在差异、接口多的问题,还要注意设计模式、理念及绘图方式的差别。 Amuzang II pumping station in Republic Of Uzbekistan is a large-scale pumping station of large flow and high lift. It is a international bidding projects by Asian Development Bank. It's single-machine capacity and total capacity are beyond example in China.In the electrical design, not only need to select main electric circuits and equip electrical equipment according to the project's practical conditions, but also to pay attention to that there are differences and excessive interfaces when foreign equipment mating with domestic product, and to the differences in design patterns, concept and drawing mode.
作者 张静
出处 《水科学与工程技术》 2013年第3期57-62,共6页 Water Sciences and Engineering Technology
关键词 Amuzang II泵站 技术改造 电气设计 AmuzanglI pumping station technical renovation electrical design
  • 相关文献

参考文献5

  • 1水电站机电设计手册编写组.水电站机电设计手册[K].北京:中国水利电力出版社,1982.
  • 2SDGJ 14-86,导体和电器选择设计技术规定[S].
  • 3GB/T50625-97,泵站设计规范[S].
  • 4戈东方.电力工程电气设计手册.电气一次部分[K].北京:中国电力出版社.1991.
  • 5钢铁企业电力设计手册编委会.钢铁企业电力设计手册[K].北京:冶金工业出版社,1986.