摘要
本文重点介绍了某电厂2×300MW机组两炉一塔烟气脱硫装置采用石灰石-石膏湿法烟气脱硫工程改造为一炉一塔的脱硫系统设计、配置及布置等设计方案,并对该工程上出现的设计难点和方案创新进行了阐述,以便为国内同类型脱硫工程改造提供借鉴作用。
It is necessary to increase the capacity of FGD plants for large numbers of coal-fired power plants in China. The main methods and the applicative cases on modification technology for capacity increment are intro- duced. The influencing factors are analyzed together with the main characteristics. The suggestions of increasing capacity are useful for modification in more and more coal-fired power plants.
出处
《化学工程师》
CAS
2012年第11期34-36,47,共4页
Chemical Engineer