通过对北京草桥燃气联合循环热电厂二期工程SFC系统特点的分析总结,以及调试中遇到的问题和解决办法的介绍,可为今后的燃气联合循环热电厂进行相关系统调试提供参考。
According to the feature of SFC system in Beijing Caoqiao Gas-fired Combined-cycle Cogeneration Power Plant phase II ,this paper introduced the problems encountered in debugging, as well as its solution method, which could be the reference for other gas-fired combined cycle cogeneration power plant in debugging of SFC system.
出处
《华北电力技术》
CAS
2013年第7期44-45,53,共3页
North China Electric Power
关键词
SFC
燃气轮机
启动
调试
SFC
gas-turbine generator
start
debugging