摘要
乌江是我国水电梯级开发最好的水电基地之一,沙沱水电站为乌江干流最后一个投入运行的大型水电站。本文通过分析沙沱水电站工程特点、上下游水库条件等,总结了沙沱水电站下闸蓄水的梯级协作调度方案,该方案也将在沙沱水电站实际下闸蓄水阶段具体实施。
Wujiang River is one of the best bases for the cascade development of hydropower; on which Shatuo Hydropower Sta- tion is the large hydropower station that puts into operation lastly. Through the analysis on the characteristics, the conditions of both the upstream and downstream reservoirs, etc. , the cascade joint-operation scheme for the impoundment of the hydropower station are summarized herein, and this scheme is to be implemented for the actual impoundment concerned.
出处
《水利水电技术》
CSCD
北大核心
2013年第8期89-93,共5页
Water Resources and Hydropower Engineering
关键词
乌江
沙沱水电站
下闸蓄水
梯级协作调度
Wujiang River
Shatuo Hydropower Station
impoundment
cascade joint-operation