摘要
依据桥梁施工顺序及工程质量控制要点,分析了影响桥梁成桥线形的各种因素,从桥梁高墩墩身线形控制、预应力管道钢筋施工等方面总结出一套完整的过程控制规划理论,同时给出了数据跟踪修正手段,并通过在乌海黄河特大桥的实例证明,该套控制手段是有效的。
Based on the bridge construction sequences and construction quality control key points, this paper analyzes the various factors influ- enced the bridge into the bridge line, from the linear control of high bridge pier, pre-stressed pipe steel bar construction and other aspects summa- rized a set of complete process control planning theory, at the same time, gave data tracking correction methods, and through the example proved the Wuhai Yellow River extra-large bridge, this set control method was effective.
出处
《山西建筑》
2013年第32期154-155,共2页
Shanxi Architecture
关键词
悬臂桥梁
高墩
施工技术
监测控制
cantilever bridge, high pier, construction technology, monitoring control