摘要
连云港金港湾国际物流园区建于沿海软土,运货车辆荷载大,对堆场的强度要求高,为探寻在软土中修建经济合理的堆场施工方案,对B型集装箱查验平台采用"超载预压"对堆场软基进行处理,研究发现该方法是合理有效的,不仅保证了质量,而且降低了造价,本文对此成功经验加以归纳,供大家参考。
Lianyungang Jingangwan international logistics park is constructed in the coastal soft soil, the freight traffic loads is large, high demands is must to the Port cargo area,For consultation in the soft soil in the economy of Port cargo area works, "Plastic drainage board and preloading" are used to processing the soft soil of the B Port cargo area, combined with the researches, Proved this method is reasonable and effective,We not only guaranteed the quantity of the reconstruction project, and the cost is lower that the budget, In this article we will share our experiences and techniques.
出处
《科技通报》
北大核心
2013年第12期157-159,共3页
Bulletin of Science and Technology
基金
江苏省建设厅基金项目(JS2008ZD03)
关键词
堆场软基
塑料排水板
超载预压
soft soil of Port cargo area
plastic draining water board
surcharse precompression