摘要
介绍了采用折叠控制爆破技术拆除水塔的实例。通过合理选择切口参数、微差爆破时间、孔网参数、药量 ,成功地迫使 41m高的水塔倒塌在长 13m的范围内。这为以后类似的工程提供了宝贵的经验。
This paper presented a successful example of collapsing a water tower using controlled blasting. By selecting the proper blasting cut parameters, delay internal, blasthole pattern parameters and charge weight, the water tower with a height of 41m was made smoothly to collapse in the area of 13m length. It provided the valuable experience for the similar projects.
出处
《工程爆破》
2000年第4期26-29,共4页
Engineering Blasting
关键词
水塔
控制爆破
折叠爆破
切口参数
爆破拆除
Water tower
Controlled blasting
Folding blasting
Blasting cut parameters