摘要
云南巍山县城原水输水管多为大高差重力有压流输水,阐述了原水输水管道改扩建工程的设计方案,包括现状输水管存在的问题、线路选择、安全防护措施、管径确定等设计内容,可供设计人员参考。
Weishan county raw water delivery pipeline is characterized by large elevation differ- ence and gravity flow with pressure. The design scheme of the raw water delivery pipeline reconstruction and expansion, including the problems of the existing pipeline, line selection, safety protection measures and pipe sizing was described to provide reference for designers.
出处
《中国给水排水》
CAS
CSCD
北大核心
2014年第10期52-54,共3页
China Water & Wastewater
关键词
原水输水管
改扩建工程
设计
raw water delivery pipeline
reconstruction and expansion project
design