论述下关电厂 2× 12 5MW机组炉内喷钙炉后活化脱硫工程的工艺原理 ,吸收剂制备、炉内喷钙、炉后活化增湿等系统的主要设备 ,运行中存在的问题及改进措施 ,工艺特点及应用前景。
The technical principles of LIFAC desulfurization project for 2×125MW units in Xiaguan Power Plant,the main equipment applied during absorbent preparation,limestone injection,activation and humidification,the main problems in operation and their improvement method,the techical characteristics and its application foreground are outlined.The technical consummation and improvement are also discussed.
出处
《电力环境保护》
2001年第2期1-7,共7页
Electric Power Environmental Protection