机械顶管施工中超挖和地面超载引起的地表沉降规律研究 被引量:12

Research on surface settlement regularity caused by over excavation and ground overloading in mechanical pipe jacking
原文传递
导出
摘要 结合某工程实例,对机械顶管施工中由于超挖和地面超载引起的地表沉降问题进行研究。按照现场实际条件确定参数,通过有限元软件建立顶管顶进模型并进行各工况模拟分析,然后将模拟结果与现场监测结果对比,以验证模型适用性。建立超挖量为30mm,地面超载为10kPa的顶进模型,模拟结果与现场监测结果基本吻合,验证了模型的适用性。分别改变单一影响因素,发现机械顶管施工中,超挖量和地面超载是影响地表沉降的两大重要因素。 Combined with an engineering example,the problem of surface settlement caused by over excavation and ground overloading in the construction of mechanical pipe jacking is studied.The parameters are determined according to the actual conditions in the field,and the jacking model of jacking pipe is established by finite element software and the simulation analysis of each condition is made.Then,the simulation results are compared with the monitoring results to ensure the applicaility of the model.A jacking model with an over excavation of 30mm and a ground overloading of 10kPa is established.The simulation results are basically consistent with the on-site monitoring results to verify the applicability of the model.Respectively,to change a single influencing factor,it is found that over-excavation and ground overloading are two important factors that affect surface settlement in the construction of mechanical pipe jacking.When the ground overloading is constant,the larger the over excavation is,the greater the settlement of the ground surface will be.When the over excavation is constant,the larger the ground overloading is,the greater the settlement of the ground surface will be.
作者 宋建学 张瑞鑫 孙宇赫 Song Jianxue;Zhang Ruixin;Sun Yuhe(School of Civil Engineering,Zhengzhou University,Zhengzhou 450001,China;Gongyi Yellow River Bureau,Gongyi 451200,China)
出处 《建筑科学》 CSCD 北大核心 2018年第11期134-139,共6页 Building Science
关键词 顶管施工 现场监测 沉降控制 数值模拟 pipe jacking construction on-site monitoring settlement control numerical simulation
  • 相关文献

参考文献3

二级参考文献32

  • 1姜忻良,赵志民,李园.隧道开挖引起土层沉降槽曲线形态的分析与计算[J].岩土力学,2004,25(10):1542-1544. 被引量:149
  • 2王承德.薄覆盖层下顶管防止地面沉降的措施[J].特种结构,1994,11(2):12-14. 被引量:2
  • 3施成华,黄林冲.顶管施工隧道扰动区土体变形计算[J].中南大学学报(自然科学版),2005,36(2):323-328. 被引量:39
  • 4余彬泉 陈传灿.顶管施工技术[M].人民交通出版社,1997..
  • 5[2]Peck R B.Deep excavations andtunnelingin soft ground[A].7th International Conference on Soil Mechanics and Foundation Engineering,Mexico City,1969,225-290.
  • 6[3]Atkinson J H,Potts D M.Subsidence above shallowtunnelsin soft ground[J].Journal of Geotechnical Engineering,1977,103(4):307-325.
  • 7[4]Loganathan N,Poulos H G.Analytical prediction for tunneling-induced ground movementin clays[J].Journal of Geotechnical and Geoenvironmental Engineering,1998,124(9):846856.
  • 8[5]Attewell P B,FarmerI W.Ground settlement above shield driventunnelsin clay[J].Tunnels and Tunnelling,1975,7(1):58-62
  • 9[8]Fang Y S, Lin S J, Lin J S. Time and settlement in EPB shield tunneling [J]. Tunnels and Tunnelling, 1993, 134( 11 ): 27-28.
  • 10[11]Sagaseta C . Analysis of undrained soil deformation due to ground loss [J]. Geotechnique, 1987, 37(3):301-320.

共引文献164

同被引文献103

引证文献12

二级引证文献32

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部