摘要
成本控制是项目管理的重要环节 ,然而 ,在实际应用中又往往很难在计算机平台上直观地表示出来 .为了解决这个难题 ,以网络图的形式表现成本费用的变化 ,提出了项目进度控制和成本控制结合的同步控制 ,目的是使成本费用能与进度控制在统一的计算机平台上动态地产生和控制 .并结合一个办公楼项目的例子的模拟 ,具体说明了控制同步的控制思想及其视图绘制方法 .
Cost control is an important aspect of project management. However, in practice, it is difficult to show by computer directly. In order to deal with this problem, we utilize a network diagram to denote the cost control of the project and apply a new technique named Synchronized control. That is, the cost control of the project was synchronized with its process control by using a network diagram. Our aim was to control the cost dynamically on singular computer basis in conjunction with process control. Synchronized cost and process control for the example of an office building was demonstrated in seven steps. It was a try to build a uniform software platform for all aspects of project management, including cost control, process control and so on.
出处
《浙江大学学报(工学版)》
EI
CAS
CSCD
北大核心
2002年第3期293-297,共5页
Journal of Zhejiang University:Engineering Science