摘要
通过对燃煤电厂双进双出钢球磨所配原煤仓运行现状进行调查,分析双出口原煤仓堵煤原因,采取相应措施,对双出口原煤仓型线进行设计优化,以达到解决或减轻双出口原煤仓堵煤的目的。
According to the research in running condition of raw coal bunker matching double-ended ball mill in coal- fired power plant,analysis the cause of the double- outlet raw coal bunker be stifled,taking optimized design,arriving at the purpose of solving or reducing the double- outlet raw coal bunker be stifled.
出处
《应用能源技术》
2014年第7期46-49,共4页
Applied Energy Technology
关键词
双出口原煤仓
堵煤
型线
设计优化
Double-outlet
Raw coal bunker
Type line
Design optimization