根据新巨龙矿井一采区第一个沿空开采综放工作面的矿压实测,论证了工作面沿空巷道围岩变形控制技术。
According to the ground pressure monitoring resuh of the first working face along goaf in first mining area of new Julong mine, demonstrates the roadway surrounding rock deformation eontrol technology along goaf.
出处
《山东煤炭科技》
2014年第7期66-68,共3页
Shandong Coal Science and Technology
关键词
沿空开采
综放工作面
矿压实测
巷道围岩
变形控制