地铁隧道大截面暗挖施工工艺及风险控制 被引量:5

MINING EXCAVATION PROCESS AND RISK CONTROL OF SUBWAY TUNNEL WITH LARGE SECTION
下载PDF
导出
摘要 北京地铁六号线二期工程起点至物资学院站区间平交段为大截面暗挖施工,其主要工序包括大管棚超前支护、双侧壁导坑法开挖支护、拱部深孔注浆加固等,针对施工难度高、风险大等特点,制订了合理的施工工艺,控制了施工风险。 Large-section mining excavation method is adopted at the plane crossing segment between the starting station and Wuzi University Station of Beijing Subway Line 6 Phase Ⅱ.The main construction steps include advance support of large tube shelter,support for excavation by double side-wall pilot tunnel method and grouting reinforcement of deep holes on arch,etc.Considering difficult construction and high risk,appropriate construction processes are established to control the construction risks.
出处 《建筑技术》 2014年第9期774-776,共3页 Architecture Technology
关键词 地铁工程 大断面暗挖 风险控制 subway project large-section mining risk control
  • 相关文献

参考文献3

  • 1JQB-050-2008,隧道工程施工质量验收标准(修订版)[S].
  • 2GB 50299-1999,地下铁道工程施工及验收规范(2003年版)[S].
  • 3DBJ 01-87-2005,北京市市政基础设施工程暗挖施工安全技术规程[S].

共引文献22

同被引文献19

引证文献5

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部