地铁车站暗挖法施工中导洞开挖方案比较 被引量:4

Comparison of Metro Station Pilot Tunnel Excavation Technologies
下载PDF
导出
摘要 目前洞桩法是浅埋暗挖地铁车站的主要施工方法,但是由于洞桩法设置的导洞多、导洞间距小,所以导洞的开挖一直是设计者和施工者探索的重要课题。以北京地铁7号线双井站八导洞开挖为工程背景,利用有限元软件Ansys建立模型,并结合现场实际监测数据对两种方案进行对比分析,得到了两种不同导洞施工方案的地表沉降变化规律,对类似工程的施工具有参考价值。 Current PBA method is the main construction meth- od of subway station. Due to redandent pilot tunnels and small pilot tunnel spacing in PBA method, the pilot tunnel excavation has been the main issue for designers and constructors. Based on the excavation engineering of eight pilot tunnelsat Shuangjing Station on Beijing metro Line 7, the finite element software Ansys is used to establish a model, which is compared with the actual monitoring data of the site, then the surface subsidence changes of two different pilot tunnel construction plans are an- alyzed, some references are put forward for similar projects.
出处 《城市轨道交通研究》 北大核心 2014年第11期103-106,112,共5页 Urban Mass Transit
关键词 洞桩法 有限元 地表沉降 pile-beam-arch (PBA) finite element surfacesubsidence
  • 相关文献

参考文献7

二级参考文献20

  • 1关金龙,萧潇.洞桩法施工车站地表沉降的有限差分法分析[J].山西建筑,2007,33(5):274-275. 被引量:6
  • 2GB 50299-1999地下铁道工程施工及验收规范[S].北京:中国计划出版社,2004.
  • 3朱维申,1986年
  • 4杨淑清,武汉水利电力学院学报,1986年,73页
  • 5杨奇,1985年
  • 6张有为,动态规划导论,1985年
  • 7俞裕泰,地下工程,1984年,11期,31页
  • 8朱维申,双轴压缩作用下雁形裂纹扩展机理及岩体加锚增韧的模型试验研究,1995年
  • 9朱维申,小浪底水利工程地下厂房洞室群分部开挖施工顺序方案优化分析,1995年
  • 10朱维申,Proceedings of the International Symposium on Anchoring and Grouting Techniques,1994年,188页

共引文献351

同被引文献27

引证文献4

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部