混合梁斜拉桥索塔与下横梁异步施工控制分析 被引量:1

Stress Analysis of Asynchronous Construction of Pylon and Bottom End Rail of Hybrid Girder Cable-stayed Bridge
下载PDF
导出
摘要 某特大桥索塔采用钻石型混凝土索塔,索塔总高度为177.91 m,在下塔柱与中塔柱相交位置设置一道下横梁。施工中塔柱与下横梁采用异步施工,即先将中塔柱施工到第二节段再进行下横梁施工。期间,索塔会出现悬臂状态,故索塔的薄弱截面易出现拉应力,这在桥梁施工中是要避免的,为此,先通过模拟分析异步施工过程对索塔的影响,给出相应的施工控制措施。 A bridge is used with the diamond type concrete pylon,and its total height is 177. 91 m. In the intersection position of the Middle-Pylon and the Down-Pylon is the bottom end rail. The construction method of the pylon and bottom end rail are asynchronous constructed,which is we put the middle-pylon into the second construction segment,and then go on the bottom end rail. During the period,pylon will appear cantilever state,so the weak section prone to tensile stress; it is to be avoided in the bridge construction. The purpose of this paper is to simulate asynchronous process,to analyze the influence to the tower,and to give the corresponding construction measures.
出处 《安庆师范学院学报(自然科学版)》 2015年第1期46-49,共4页 Journal of Anqing Teachers College(Natural Science Edition)
基金 中央财政支持的建筑技术实训基地项目(34113042613) 安徽省教育厅 财政厅支持的省级示范实验实训中心项目(20101474)
关键词 混合梁斜拉桥 索塔 异步施工 主动支撑 施工阶段 hybrid girder cable-stayed bridge tower asynchronous construction active support construction stage
  • 相关文献

参考文献8

二级参考文献7

共引文献33

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部