项目资源均衡研究综述 被引量:18

A literature survey of project resource leveling
原文传递
导出
摘要 作为一类经典的项目调度问题,资源均衡研究的是如何通过安排活动来均衡整个项目周期内资源的使用.资源均衡问题因其重要的理论价值和应用背景,一直是项目调度领域的重点研究课题.鉴于此,对国内外项目资源均衡的研究成果进行了系统性总结与梳理:介绍了资源均衡问题的数学模型和常用的测试问题库;综述了求解资源均衡问题的各类算法;总结了资源均衡问题的一些扩展问题和应用情况.最后指出了未来进一步的研究方向. The resource leveling problem is a class of classical project scheduling problems, which aims at leveling the resource usages over the project horizon by scheduling activities. Because of the theoretical importance and the practice background, the resource leveling problem has been attracting many research efforts. Therefore, a literature review of the research on the area of resource leveling is proposed. Firstly, the mathematical model of the resource leveling problem and some standard test instances are introduced. The algorithms for solving the resource leveling problem are reviewed. The extensions and applications of the resource leveling problem are surveyed. Finally, some future research directions are presented.
出处 《控制与决策》 EI CSCD 北大核心 2015年第5期769-779,共11页 Control and Decision
基金 教育部人文社会科学研究规划基金项目(12YJA630158) 上海市软科学研究计划重点项目(14692105900)
关键词 项目调度 资源均衡 算法 综述 project scheduling resource leveling algorithms survey
  • 相关文献

参考文献75

  • 1Demeulemeester E, Herroelen W. Project scheduling: A research handbook[M]. New York: Kluwer Academic Publishers, 2002: 368.
  • 2方晨,王凌.资源约束项目调度研究综述[J].控制与决策,2010,25(5):641-650. 被引量:47
  • 3Sprecher A, Kolisch R, Drexl A. Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem[J]. European J of Operational Research, 1995, 80(1): 94-102.
  • 4Neumann K, Schwindt C, Zimmermann J. Project scheduling with time windows and scarce resources: Temporal and resource-constrained project scheduling with regular and nouregular objective functions[M]. Berlin: Springer, 2003: 242.
  • 5Burgess A R, Killebrew J B. Variation in activity level on a cyclical arrow diagram[J]. J of Industrial Engineering, 1962, 13(2): 76-83.
  • 6Woodworth B M, Willie C J. A heuristic algorithm for resource leveling in multi-project, multi-resource scheduling[J]. Decision Sciences, 1975, 6(3): 525-540.
  • 7Harris R B. Packing method for resource leveling (PACK)[J]. J of Construction Engineering and Management, 1990, 116(2): 331-350.
  • 8Hegazy T. Optimization of resource allocation and leveling using genetic algorithms[J]. J of Construction Engineering and Management, 1999, 125(3): 167-175.
  • 9Neumann K, Zimmermann J. Resource levelling for projects with schedule-dependent time windows[J]. European J of Operational Research, 1999, 117(3): 591- 605.
  • 10Neumann K, Zimmermann J. Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints[J]. European J of Operfftional Research, 2000, 127(2): 425-443.

二级参考文献177

共引文献210

同被引文献133

引证文献18

二级引证文献48

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部