摘要
为保证某电厂取水安全可靠且尽量减少取水对防洪的影响,通过模型试验,对比研究了天然河道取水(泵船)和其他辅助措施取水方式(闸坝)下河道水流流态和泥沙淤积的变化规律。结果表明,闸坝取水方案和泵船取水方案均能满足取水防沙的要求,但闸坝取水方案优于泵船取水方案。
In order to ensure water intaking of a certain power plant safety and reliability, and reduce its impact on the flood prevention, the flow pattern and sediment transport characleristics of pump ship and gate dam intaking schemes were studied by model test. The results indicate that both water intaking schemes could meet the requirements of sand prevention, but the gate dam scheme is better.
出处
《水电能源科学》
北大核心
2015年第6期136-138,共3页
Water Resources and Power
基金
国家自然科学基金项目(51279117)