北京地铁剪切型减振器扣件钢轨波磨治理的试验研究 被引量:21

Test Study on Treating Rail Corrugation for Egg Fastener in Beijing Metro
下载PDF
导出
摘要 北京地铁近年来投入运营的几条线路中,剪切型减振器扣件区段大量出现钢轨波磨现象,经过大量的调查和测试分析发现:剪切型减振器扣件轨道系统在200-400Hz频段内的轮轨共振效应是引发钢轨波磨的主要原因。为了抑制波磨发展,在剪切型减振器扣件内增设橡胶垫块,并在北京地铁10号线选择两个试验段进行了现场试验,对两个试验段的钢轨走形带粗糙度进行了为期6个月的跟踪测试。测试结果表明:在剪切型减振器扣件内增设橡胶垫块有效地控制了钢轨波磨的发展,并在一定程度上起到了消减钢轨波磨的作用。 The rail corrugation on the track using Egg fastener becomes a serious problem on several operated lines of Beijing metro in recent years. The investigations and field measurements show the corrugation is mainly induced by the resonance vibration in the train/track system at 200-400 Hz. To suppress the growth of corrugation, a rubber pad is installed in Egg fastener. And two field tests are carried out on line 10 of Beijing metro to evaluate the effect of treating the rail corrugation. The running band roughness of corrugated rail in the test sections has been measured for about 6 mouths. The measurement results show that the measure of installing a rubber pad in Egg fastener is an effective treatment for controlling the growth of rail corrugation or reducing the corrugation to some degree.
出处 《机械工程学报》 EI CAS CSCD 北大核心 2015年第21期73-79,共7页 Journal of Mechanical Engineering
基金 国家自然科学基金资助项目(51378001)
关键词 地铁 钢轨波磨 剪切型减振器扣件 现场试验 metro rail corrugation Egg fastener field test
  • 相关文献

参考文献22

  • 1任静,孙京健,陈鹏,王进.从钢轨异常波磨研究反思地铁设计[J].都市快轨交通,2011,24(3):2-5. 被引量:12
  • 2刘维宁,任静,刘卫丰,王文斌,张厚贵.北京地铁钢轨波磨测试分析[J].都市快轨交通,2011,24(3):6-9. 被引量:41
  • 3郭建平,刘维宁,雷黔湘,张艳军.北京地铁4号线钢轨异常波磨调查及整治措施[J].都市快轨交通,2011,24(3):10-13. 被引量:22
  • 4ZHANG Hougui, LIU Weining, LIU Weifeng, et al. Studyon the cause and treatment of rail corrugation for Beijing metro[J].Wear, 2014, 317(1-2): 120-128.
  • 5GRASSIE S L, KALOUSEK J. Rail corrugation: Characteristics, causes and treatments[J]. Proceedings of the Institution of Mechanical Engineers, Part F: Journal of Rail and Rapid Transit, 1993, 207: 57-68.
  • 6GRASSIE S L. Rail corrugation: Characteristics, causes and treatments[J]. Proceedings of the Institution of Mechanical Engineers, Part F: Journal of Rail and Rapid Transit, 2009, 223(6): 581-596.
  • 7EADIE D, KALOUSEK J, CHIDDICK K. The role of high positive friction (HPF) modifier in the control of short pitch corrugations and related phenomena[J]. Wear, 2002, 253(1-2): 185-192.
  • 8TOMEOKA M, KABE N, TANIMOTO M, et al. Friction control between wheel and rail by means of on board lubrication[J].Wear, 2002, 253(1-2): 124-129.
  • 9HEYDER R, GIRSCH G~ Testing of HSH~ rails in high-speed tracks to minimize rail damage[J]. Wear, 2005, 258(7-8): 1014-1021.
  • 10HIENSCH M, NIELSEN J C O, VERHEIJEN E. Rail corrugation in the Netherlands-measurements and simul ations[J]. Wear, 2002, 253(1-2): 140-149.

二级参考文献41

  • 1GB50157--2003地铁设计规范[S].北京:中国计划出版社.2003.
  • 2机械设计手册编委会.机械设计手册[M].北京:机械工业出版社,2001.
  • 3TB10082--2005铁路轨道设计规范[S].北京:中国铁道出版社.2005.
  • 4Egana J I, Vinolas J, Seco M. Investigation of the influence of rail pad stiffness on rail corrugation on a transit system [J]. Wear, 2006, 261:216-224.
  • 5Grassie S L, Gregory R W, Johnson K L. The dynamic response of railway track to high frequency vertical excitation [J]. Mech. Eng. Sci, 1982(24):77-90.
  • 6Tassilly E, Vincent N. Rail corrugations: analytical model and field tests[J]. Wear, 1991,144:153 - 161.
  • 7北京轨道交通减少异常渡磨综合减振技术研究课题组.北京地铁5号线钢轨波磨调查报告[R].北京:北京交通大学,2010.
  • 8铁道第四勘察设计院.北京地铁四号线环境影响评价报告书[R].北京,2004.
  • 9北京城建设计研究总院有限责任公司.北京地铁5号线钢轨波磨调研报告[R],2010.
  • 10Ahlberk D R, Daniesl L E. Investigation of rail corrugaion on the bahimore metro wear[ J]. 1991,144 : 197 - 210.

共引文献101

同被引文献137

引证文献21

二级引证文献86

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部