港珠澳海底沉管隧道近陆域段管节防护设计 被引量:3

Design of Backfill Protection of Near-land Section of Immersed Tunnel of Hongkong-Zhuhai-Macao Link
下载PDF
导出
摘要 沉管隧道的回填防护根据功能需求,在纵向上可按照普通段、航道段及近陆域段3个分区进行防护。近陆域段防护需要考虑的影响因素多,且安全风险高,是沉管隧道工程防护设计的重点。以正在建设的港珠澳跨海通道工程中海底沉管隧道近人工岛陆域段的回填防护为研究对象,针对近陆域段采用柔性与刚性2种防护方案进行研究比选,提出适合项目特点的护坦潜堤式柔性防护方案,并详细分析了柔性防护方案的设计细节,通过防撞、防锚及稳定性方面的计算分析以及工程实践,证明这种防护方式是科学合理的。 Based on the function requirement,the backfill protection of immersed tunnels can be divided into three sections,i.e.,normal section,navigation channel section and near-land section.Among these sections,the design of the near-land section is influenced by many factors,therefore it is the key part of the design of the backfill protection of immersed tunnels.In the paper,the backfill protection of the near-artificial-island section of the immersed tunnel of Hongkong-Zhuhai-Macao Link is studied,comparison and contrast is made between flexible protection and rigid protection,and a flexible solution is proposed for the project.Furthermore,the design details of the flexible protection solution are provided.Calculations and tests show that this type of protection is rational and can be used for other similar projects.
出处 《隧道建设》 北大核心 2015年第11期1188-1193,共6页 Tunnel Construction
关键词 沉管隧道 近陆域段 管节防护 刚性防护 柔性防护 防撞 稳定性 immersed tunnel near-land section backfill protection rigid protection flexible protection ship collision stability
  • 相关文献

参考文献10

二级参考文献27

  • 1傅琼阁.沉管隧道的发展与展望[J].中国港湾建设,2004,24(5):53-58. 被引量:43
  • 2管敏鑫.钢筋混凝土沉管隧道在设计与施工中的有关问题[J].现代隧道技术,2007,44(1):1-4. 被引量:5
  • 3ITA Work Group. Immersed and floating tunnels [ J ]. Tun- nelling and Underground Space Technology, 1997,12 (2): 93 - 109.
  • 4The Oresund techinical publication. Tunnel [ M ]. Oresunds- bro Konsortiet, 2001.
  • 5Chris Marshall. The Oresund tunnel: Making a success of design and build [ J ]. Tunnelling and Underground Space Technology, 1999,14(3) :355 - 365.
  • 6W P S Janssen, Steen Lykke. The fixed link across the Ore- sund: Tunnel section under the Drogden [ J ]. Tunnelling and Underground Space Technology," 1997,12( 1 ) :5 - 14.
  • 7W Jassen, P de Haas, Y H Yoon. Busan-Geoje Link: Im- mersed tunnel opening horizons [ J ]. Tunnelling and Under- ground Space Technology,2006,21 (3) : 332.
  • 8L C F Ingerslev. Considerations and strategies behind the design and construction requirements of the Istanbul Strait immersed tunnel [ J ]. Tunnelling and Underground Space Technology, 2005,20 (6) : 604 - 608.
  • 9JTJ215-98.港口工程荷载规范[S].[S].,..
  • 10JTJ298-98.防波堤设计与施工规范[S].[S].,..

共引文献111

同被引文献11

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部