新建核电站模拟机建造风险分析及对策 被引量:4

The new Built Nuclear Power Plant Simulator Development Risk Analysis and Countermeasures
下载PDF
导出
摘要 模拟机按期可用于培训是核电站建设二级里程碑关键进度节点,其能否按期完成建造、测试并被批准可用于培训将直接影响到电站操纵员培训、考试、取照进度,进而影响到后续整个电站建设进度。本文通过对三门核电AP1000全范围模拟机建设过程中出现的风险、问题进行全面分析、总结,进而对如何控制新建电站全范围模拟机的建造风险给出了建议方案。 The simulator ready for training is one key point of the nuclear power plant construction level two milestone progress schedule ,whether the simulator can be built, tested and approved for training on time will directly impact the progress of the nuclear power plant operator training , examination and licensing, further will impact the whole nuclear power plant construction progress . This article comprehensively analyses the problem and risk of Sanmen nuclear power plant full scope simulator built process, farther gives the suggestion plan on how to control the risk of the new built nuclear power plant simulator.
出处 《仪器仪表用户》 2015年第6期5-7,14,共4页 Instrumentation
关键词 模拟机 进度 风险控制 simulator progress risk control
  • 相关文献

参考文献7

二级参考文献7

  • 1周刚,伊雄鹰.核动力仿真技术及其发展[J].原子能科学技术,2006,40(B09):23-29. 被引量:6
  • 2Jin Joo Lee, Paul A. Fishwick. Real-Time Simulation-Based Planning for Computer Generated Force Simulation[R], 1994: 10-63.
  • 3Richard H. Hill. Simulation, emulation, & translation[J], SIMULATION Feb 1968, 10: 81- 84.
  • 4王明新,邹沫元.现代仿真技术在核电工业中的应用与发展[A].中国核学会2001年学术年会论文集[c].武汉:中国核学会,2001:89-92.
  • 5周维长.仿真技术在核电中的综合应用[A].2001年全国仿真技术学术会议论文集[C].2001:280-283.
  • 6任宏,张巍.工程项目管理[M].北京:高等教育出版社,2006,10:228-278.
  • 7王朝金,陈松.浅谈工程项目管理[J].今日科苑,2008(10):103-103. 被引量:2

共引文献26

同被引文献11

引证文献4

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部