摘要
通过对国内首台自主改进型300 MW循环流化床机组甩负荷试验的研究,针对该型机组独有的设计特点,分析了甩负荷试验中存在的再热器超温、旁路控制、高排温度高等危险点,提出了顺利完成试验的控制要点和注意事项。
Based on the research to one 300 MW unit using the first autonomously improved CFB boiler in the nation, the dangerous points such as the overheat of reheater, the control of bypass, the control of exhaust temperature of high pressure cylinder has been analyzed, the control main point and the matters need attention have also been given.
出处
《贵州电力技术》
2015年第12期11-14,共4页
Guizhou Electric Power Technology