某H码头工程建设对长江行洪影响分析 被引量:2

Impact of H Wharf Construction on Flood Discharge in Yangtze River
下载PDF
导出
摘要 本文以长江左岸某拟建H码头工程为例,在MIKE软件平台上建立H码头河段内二维水流数学模型,对H码头兴建前后河段内水流的流态、壅水高度以及流速、流向进行了计算分析研究.H码头建成后,河段内的水位雍高值不超过0.01m;水流流速和流态均无明显变化,且其受影响范围都介于工程上游400m至下游800m范围内.研究结果表明该H码头工程的建设对其所在河段的河势及行洪不会产生明显不利影响. A 2Dflow mathematical model,prototyped from a planned H wharf in the Yangtze River,was built in the software MIKE.Simulations and investigations were conducted with respect to the flow patterns,backwater and velocity inside this model,aiming at a detailed evaluation of the impacts on the flood discharge due to the construction of the H wharf.The results show that after the H wharf construction,the values of backwater in the whole region are less than 0.01m;water velocity and flow patterns have no obvious change;the affected region range is within the 400 mupstream to 800 mdownstream with respect to the H wharf’s location.It is indicated that the construction of the H wharf will have no obvious impacts on the flood discharge and flow patterns in this river reach.
出处 《三峡大学学报(自然科学版)》 CAS 2016年第1期6-10,共5页 Journal of China Three Gorges University:Natural Sciences
基金 教育部创新团队发展计划(IRT1233) 鱼道内鱼类运动机理研究和过鱼效果评价(KF2015-01) 中国国家自然科学基金(51409151)
关键词 二维水流数学模型 防洪影响评价 H码头工程 雍高 2D flow mathematical model evaluation of flood control H wharf engineering backwater
  • 相关文献

参考文献12

二级参考文献36

共引文献53

同被引文献13

引证文献2

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部