摘要 传统的沉箱浮游稳定计算公式繁琐、复杂,且没有形成统一的方法。以大连金龙湾护岸工程为例,阐述了BIM技术计算大型圆沉箱浮游稳定的方法,计算准确、快捷、灵活,达到了预期的效果,可供类似项目借鉴。 It is always tedious and complicated to calculate buoyant stability of caissons by using the traditional computations and yet there is no unified approach which has been recognized. In order to find a rapid method for calculation of buoyant stability of caissons,taking as an example the revetment works for Jinlong Bay in Dalian,the paper introduces the application of BIM technology in calculating buoyant stability of large circular caissons. The result turns to be satisfactory as BIM technology not only shows accuracy of calculation, but also brings convenience and flexibility, which can also be used in other similar projects.
出处 《中国港湾建设》 2016年第5期6-8,共3页 China Harbour Engineering
关键词 BIM 沉箱 浮游稳定 BIM caisson buoyant stability
  • 相关文献

参考文献4

二级参考文献4

  • 1华东水利学院.水工设计手册[M].北京:水利水电出版社,1983.637-647.
  • 2杨文渊 徐(牛牛).桥梁施工工程师手册[M].北京:人民交通出版社,1999..
  • 3JTJ 290-1998,重力式码头设计与施工规范[S].
  • 4武汉水利水电学院建筑力学教研组.材料力学[M].北京:人民教育出版社,1961.

共引文献76

同被引文献40

引证文献3

二级引证文献45

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部