地面出入式盾构法隧道技术(GPST)施工变形监测与分析研究 被引量:8

Ground Penetrating Shield Technology Construction Deformation Monitoring & Analysis Research
下载PDF
导出
摘要 以南京至高淳城际快速轨道南京南站至禄口机场段TA01-2标工程为背景,应用地面出入式盾构法隧道技术(GPST),在负覆土、浅覆土工况下针对隧道管片和周围土层进行监测。监测结果表明:地面出入段隧道变形控制在0.4%以内,盾构超浅覆土区段掘进与浅覆土工况下的发展趋势相一致。通过分析获得负覆土工况下稳定后的横断面地表变形曲线分布规律。研究结果为盾构施工过程的参数优化提供依据,使盾构施工对周围土体的影响处于可控状态。 With the background of Bid TA01-2(Nanjing-Gaochun Intercity Rapid Rail Nanjing South Railway Station-the Lukou Airport section) Engineering,ground penetrating shield technology(GPST) is applied and tunnel lining and surrounding soil in the condition of negative covering soil and shallow overburden are monitored.The monitoring results show that the deformation control of the tunnel in ground entryexit section is less than 0.4%,and the development trend of the shield super shallow overburden section is consistent with the one of the shallow overburden soil condition.The distribution law of the surface deformation curve of the cross section under the condition of stable negative soil overburden is obtained by analyzing.The research results provide the basis for the parameter optimization of the shield construction process,so that the influence of the shield construction to the surrounding soil is controlled.
作者 滕丽
出处 《中国市政工程》 2016年第3期100-103,129,共4页 China Municipal Engineering
基金 上海市科委科技创新行动计划项目(11231202700)
关键词 地面出入式盾构法隧道技术(GPST) 监测 隧道变形 ground penetrating shield technology(GPST) monitoring tunnel deformation
  • 相关文献

参考文献2

二级参考文献18

  • 1赵峻,戴海蛟.盾构法隧道软土地层盾构进出洞施工技术[J].岩石力学与工程学报,2004,23(z2):5147-5152. 被引量:44
  • 2唐贤海,董子龙,陈潮学.黏土地层条件下盾构始发端头井加固技术[J].建筑机械化,2012,33(S2):233-235. 被引量:2
  • 3廖一蕾,张子新,张冠军.大直径盾构进出洞加固体稳定性判别方法研究[J].岩土力学,2011,32(S2):256-260. 被引量:12
  • 4李治国,周明发,王海,王书雄.天津海河共同沟隧道盾构始发井注浆堵水加固技术[J].地下工程与隧道,2009,0(S1):72-75. 被引量:7
  • 5张风祥,朱合华,傅德明.盾构隧道[M].北京:人民交通出版社,2004.
  • 6周文波.盾构进出洞施工风险分析及防治[C].//地下工程建设与环境和谐发展论文集,2009.
  • 7BEIJER A J. Ultra rapid under pass: the adaptation of the URUP method for the Netherlands[Ph. D Thesis][D]. Netherlands.. Delft University of Technology, 2010.
  • 8TOSHIO T, K1NSAKU K, KEIZO M. Construction ofMRT chaloem ratchamongldaon line underground structures north and Japanese shield tunnel technology[C]//International Symposium on Underground Excavation and Tunnelling. Bangkok, Thailand: ITA, 2006:47 56.
  • 9MIKI K, YOKOMIZO F, UEDA H, et al. Development of construction method for a road underpass at intersection[C]//World Tunneling Congress. Budapest, Hungary: ITA, 2009:31-35.
  • 10HITONARI F, TETSUYA N, MASAYOSHI I. URUP(ultra rapid under pass) method-the first shield ttameling method for launching and arrival at the ground level[C]// World Tunneling Congress. Budapest, Hungary: ITA, 2009: 112- 116.

共引文献31

同被引文献70

引证文献8

二级引证文献71

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部