摘要
闲林水库工程的输水系统与引水人城工程输水隧洞相结合,采用闲林水库上游有压输水隧洞接下游引水入城无压隧洞的输水方式,消能方式相对较为复杂。选用国内常用机械消能和水工消能等多种方式进行详细比较,结合工程管理最终选择消力池水工消能方式,结果可供类似输水工程参考。
The water diversion system of Xianlin reservoir project is combined with water conveyance tunnel in the project of drawing water. The water conveyance tunnel with pressure is applied on the upstream of the Xianlin reservoir, and then the energy dissipation mode is relatively complex. The mechanical and hydraulic energy dissipation modes and other commonly used modes are selected and compared. The stilling basin hydraulic energy dissipation modes combined with the engineering management is selected at last, and the result can he used for reference in the similar water conveyance project
出处
《南水北调与水利科技》
CAS
CSCD
北大核心
2015年第B02期267-269,共3页
South-to-North Water Transfers and Water Science & Technology
关键词
输水工程
机械消能
水工消能
消力池
water diversion project
mechanical energy dissipation
hydraulic energy dissipation
stilling basin