核电站P320系统电缆屏蔽及接地方式的改造

Transform of Cable Shielding and Grounding of P320 System in Nuclear Power Plant
下载PDF
导出
摘要 本文针对核电机组汽轮机调试期间在某功率平台稳定时发生蒸汽调节阀门波动的问题进行分析,发现汽轮机控制和保护系统(P320)的信号电缆屏蔽及接地方式存在缺陷,存在重大跳机跳堆隐患,同时可能对堆芯功率造成非常大的扰动,甚至存在触发安注的风险,威胁着堆芯的安全。考虑到其对核电机组安全稳定运行的重大影响,通过对P320系统相关信号屏蔽及接地方式进行改造,避免了因蒸汽调节阀门波动对机组的重大影响,确保了机组的长期安全稳定运行。 This article analyzed the steam regulating valve fluctuation problem on a stable power platform during nuclear power steam turbine debugging, and found that the turbine control and protection system (P320) signal cable shielding and grounding method was flawed, and there was big trip risk, and it may cause big disturbance to the core power, and can even trigger injection, threatening the safety of the reactor core. Considering the major effect on the safe and stable operation of nuclear power unit, by transforming the related signal shielding and grounding method of P320 system, the effect of steam regulating valve fluctuations is avoided to ensure the long-term safe and stable operation of the unit.
作者 李俊宁 吴琼
出处 《价值工程》 2016年第22期133-135,共3页 Value Engineering
关键词 P320系统 屏蔽 接地 改造 P320 system shielding grounding transform
  • 相关文献

参考文献2

二级参考文献15

共引文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部