摘要
北京雁栖湖国际会展中心总建筑面积79000m^2,高32m,工程结构实体工程量大,空间造型复杂,且多部位、多单位、多工种同时施工,施工难度大。通过BIM平台进行三维建模,分专业深化设计,勘误工程量计算,信息化管理现场施工资料,提升了精细化管理水平,实现了技术创效。
Beijing Yanqi Lake International Convention and Exhibition Center is 32m high, covering a gross building area of 79000m2. The structure has complex spatial shape and heavy workload, encountering great construction difficulty due to simultaneous construction of different positions, units and disciplines. Tridimensional model was established by using BIM technique to realize in-depth design of different disciplines, verify workload calculation and conduct information-based management of site construction data. Refined management level was improved and innovative technical effects were realized.
出处
《建筑技术》
北大核心
2016年第8期701-704,共4页
Architecture Technology
关键词
BIM
三维模型
施工模拟
深化设计
BIM
three-dimensional model
construction simulation
in-depth design