深基坑排桩支护计算时考虑桩间土摩擦阻力,可减少桩在基坑底的锚固深度及桩的弯矩,大量节省工程量,降低工程造价。
Deep foundation consider frictional resistance between piles soldier pile retaining calculation, a large reduction in the pile moment anchoring depth ofexcavation and pile bottom, larger quantities savings , reduce project eost.
出处
《建筑技术开发》
2017年第1期14-15,共2页
Building Technology Development
关键词
桩间土挡墙
桩间土挡墙摩擦阻力
深基坑
pile-soil retaining wall
frictional resistance between the pile and soil retaining wall
deep foundation pit