期刊文献+

复杂条件下深基坑沉箱止水井点降水施工技术 被引量:9

CAISSON WATER-STOP AND WELL POINT DEWATERING CONSTRUCTION TECHNIQUE IN DEEP FOUNDATION PIT UNDER COMPLEX CONDITIONS
下载PDF
导出
摘要 南宁万汇华府基坑施工中,针对多层地下水及防空洞的复杂条件,同步采用井点降水+钢板,局部辅助堵漏的施工方法,在短期内满足混凝土浇筑要求,节省了工期,保证了质量,并降低成本74 940元,该做法已获批广西自治区级工法,社会效益良好。 Considering the complex conditions of multi-layer groundwater and air-raid shelter during foundation pit construction of Nanning Wanhui Mansion project, well point dewatering technique and steel plate were synchronously used and auxiliary local blocking method was adopted to satisfy the short-term concrete pouring requirements, shorten the construction schedule and guarantee construction quality. RMB 74?940 construction cost was saved. This construction process has been granted as the municipal construction method of Guangxi Zhuang Autonomous Region, realizing favorable social benefits.
作者 马南湘 马骏
出处 《建筑技术》 北大核心 2017年第3期243-244,共2页 Architecture Technology
基金 广西高校科研一般项目资助<校企建筑业工法和QC开发建设与转化应用研究>(YB2014520)
关键词 深基坑 沉箱止水 井点降水 deep foundation pit caisson water stop well point dewatering
  • 相关文献

参考文献1

二级参考文献2

共引文献6

同被引文献50

引证文献9

二级引证文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部