虹吸井是电厂供水流程中非常重要的一部分,虹吸井的设置可降低循环水泵的扬程,节约电耗。设计基于某电厂工程资料,通过实验室模拟选型,从虹吸井占地尺寸、虹吸的有效利用高度、建设的投资费用、水流流态,以及电厂的经济运行等方面综合分析,得出了虹吸井的优化尺寸。
Siphon well is a very important part in the process of power plant water supply, it can reduce the lift of circulating pump, save power consumption.Based on data of apower plant, through laboratory simulation model ,study on the dimension, effective siphon height,instruction cost of the siphon well, flow pattern of water, and the economic operation pattern of the power plant, an optimization size of the siphon well is obtained.