基键链方法在模具项目管理中的应用 被引量:1

Application of Critical Chain Method in Mold Development Project Management
下载PDF
导出
摘要 分析了模具开发项目管理的特点,将关键链方法引入模具项目进度管理,通过实际案例应用,探讨了关键链识别、缓冲大小计算和监控等问题,并与传统关键路径法进行了对比。 Analysis of the characteristics of mold development project management, Critical Chain Management is introduced through the application of case. Discuss the process of identifying critical chain, buffer calculation and monitoring, and compare with the critical path method.
作者 陈晨 张新艳
出处 《模具制造》 2017年第7期1-4,共4页 Die & Mould Manufacture
关键词 模具项目管理 关键链 应用 mold project management critical chain application
  • 相关文献

参考文献4

二级参考文献22

  • 1刘士新,宋健海,唐加福.基于关键链的资源受限项目调度新方法[J].自动化学报,2006,32(1):60-66. 被引量:63
  • 2刘士新,宋健海,唐加福.资源受限项目调度中缓冲区的设定方法[J].系统工程学报,2006,21(4):381-386. 被引量:70
  • 3Goldratt E. Critical Chain[M]. The North River Press, Great Barrington, 1997.
  • 4Mabin V J, Balderstone S J. The world of the theory of constraints: A review of the international literature [M]. APICS series on Constraints Management. New York: StLucie Press, 2000.
  • 5Leach L P. Critical chain project management improves project performance[J]. Project Management Journal, 1999, 30 (2) : 39-51.
  • 6Herroelen W, Leus R. On the merits and pitfalls of critical chain scheduling[J]. Journal of Operations Management, 2001, 19(5) ,559-577.
  • 7Yeo K T,Ning J H. Integrating supply chain and critical chain concepts in engineer-procure-construct (EPC) projects [J]. International Journal of Project Management, 2002, 20 (4) : 253-262.
  • 8Wei C C, Liu P H, Tsai Y C. Resource-constrained project management using enhanced theory of constraint[J ]. International Journal of Project Management, 2002, 20: 561-567.
  • 9Newbold R C. Project Management in the Fast Lane- Applying the Theory of Constraints[M]. The St. Lucie Press, Boca Raton, 1998.
  • 10Leach L P. Critical Chain Project Management [M]. Artech House, 2000.

共引文献44

同被引文献4

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部