摘要
在充分分析韩桥实业工业广场原供电系统现状的基础上,进行了供电改造必要性分析,提出了"取消配电站,采用高压线路直接下线方式"的项目改造方案,实施并通过了项目验收及送电使用,达到了设计和验收规定要求,实现了变电所无人值守,满足了高效安全运行,降低了费用成本,取得了良好的使用效果。
Based on Square, to analyze "cancel distribution full analysis of the current situation of primary power supply system of Hanqiao Industrial the necessity of power transformation, to put forward the project modification scheme of station, and high voltage line direct referrals were adopted", implementation and acceptance of the project and use of power transmission, to meet the design and acceptance requirements,to realize unmanned substation,which was met efficient and safe operation, reduce the cost, and achieved good results.
出处
《煤炭科技》
2017年第2期155-157,共3页
Coal Science & Technology Magazine
关键词
工业广场
高压
供电
改造
industrial square
high voltage
power supply
transformation