摘要
经过科学研究和试验,找出了一种在溢流堰施工中,通过把块石嵌入混凝土,使得块石露出溢流堰水平段表面,从而消除动能的方式消能,达到了保护溢流堰的目的。在工程完工后,我们总结了嵌石混凝土的施工经验,形成了"嵌石混凝土施工工法"。
! The following mode for energy disi]3ation is discovered through scientific research and experiment stones from overflow weir horizontal section surface in the overflow weir construction through embedding stones in concreeliminating kinetic energy and reaching the purpose of protecting the overflow weir. After the project is completed, wesummarize construction experience of stone concrete and form ' construction method of stone concrete ’ .
出处
《中国水能及电气化》
2017年第10期46-53,共8页
China Water Power & Electrification
关键词
溢流堰
嵌石混凝土
overflow weir
stone concrete