摘要
针对电气设备存在质量存在差异,传统的变电验收业务没有统一的术语和技术规范的问题。结合变电验收《通用管理规定》的要求,讨论了新建变电站的验收过程和标准。论述了变电验收的可研初设审查、厂内验收、到货验收、隐蔽工程验收、中间验收、竣工验收、启动验收等7个流程以及变电验收总标准和要点,从变电验收的准备工作开始,介绍了现场验收和投入运行后的主要工作,并以电流互感器的验收为例分析了新建变电站的验收流程。
As the design of electrical equipment varied,the quality is uneven,and the problem of no uniform terminology and technical specifications in traditional substation acceptance business.This paper combined with the requirements of 《general management requirements》,and study the general criteria for acceptance.First of all,the paper discusses the seven processes of the feasibility study,the acceptance of the factory,the acceptance of the factory,the acceptance of the hidden project,the middle acceptance,the completion and acceptance,the start acceptance,and also the general criteria for acceptance.Began with the acceptance of the acceptance work,introduced the on-site acceptance and put into operation after the work,and use the current transformer as an example to detail the whole acceptance process for new substation.
出处
《电子科技》
2017年第12期136-138,共3页
Electronic Science and Technology
关键词
新建变电站
验收
验收标准
输变电设备
transformer substation
acceptance
acceptance criteria
power transmission equipment