摘要 介绍了抽水蓄能变速机组在电网中的优势,并分析探讨了变速机组在负荷集中区域、新能源集中区域以及特高压受端区域电网中所起的作用。通过对抽水蓄能变速机组的规划研究发现,负荷集中区域、新能源集中区域以及特高压集中区域,由于其特殊性对电网的安全稳定要求更高,更需要抽水蓄能变速机组的加入。以京津及冀北电网为典型电网,选取尚义抽水蓄能电站作为典型案例,对电网对变速机组的需求进行了验证,结果表明,可变速抽蓄机组调节精度高、响应速度快、调节幅度大,有利于促进京津及冀北电网坚强智能电网的建设,且从系统经济性及长远看,变速机组还是比较经济的。 The advantages of variable speed units of pumped-storage power station in power grid are introduced, and the roles of variable speed units in the areas with concentrated load and concentrated new energy and the receiving area of uhra-high voltage power network are analyzed. The research finds that, because of higher requirements for grid security and stability in above areas, the variable speed units of pumped-storage power are urgently demanded by power grid. Taking Shangyi Pumped-storage Power Station as study case, the demand on variable speed units of Beijing-Tianjin-Northern Hebei power grid is verified. The research result shows that the variable speed unit has high regulation accuracy, fast response and large adjustment range, and is conducive to promoting the construction of smart grid in Beijing-Tianjin-Northern Hebei area. The variable speed unit is also more economical from the view of system economy and long-term operation.
作者 赵杰君 栾凤奎 杨霄霄 ZHAO Jiejun 1, LUAN Fengkui2, YANG Xiaoxiao1(1. PowerChina Beijing Engineering Corporation Limited, Beijing 100024, China; 2. State Grid Corporation of China, Beijing 100031, Chin)
出处 《水力发电》 北大核心 2018年第4期57-59,共3页 Water Power
基金 国家电网公司科技项目(大型抽水蓄能灵活控制关键技术研究)
关键词 抽水蓄能 变速机组 前期规划 pumped-storage power variable speed unit preliminary planning
  • 相关文献

参考文献2

二级参考文献4

共引文献26

同被引文献98

引证文献11

二级引证文献73

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部