摘要
青岛胶南水城110kV变电站为山东省首座景观式变电站。通过对平面布置规划、建筑设计与景观一并考虑,外立面造型设计为人工绿化景观式外挂构架,优化主接线和布局,应用单母线四分段接线、创新采用主变"面对面"布置方式实现紧凑化布局。压缩建筑面积147m^2,容积率仅为0.535,相比概算节约资金161万元,实现了"与环境和谐,与居民友善",为城市中心景观式变电站的规划设计提供了参考。
Qingdao Jiaonan Shuicheng 110KV substation has been designed as the first landscape type substation in Shandong province.By combining the layout planning,architectural design and landscape,the facade is designed as an artificial landscape type external structure.The main wiring and layout is optimized by adopting four piecewise connection type of single busbar and "face to face"arrangement for the main transformer to realize the compact layout.The construction area is compressed to 147m^2,the rate of volume measurement is 0.535.Comparing to the estimated cost, it saves 1.61 million Chinese Yuan.It full fills the concept of "harmony with the environment,friendly to the people"and provides a feasible reference for design of the landscape substation in city centers.
作者
高岩
GAO Yan(State Grid Qingdao Power Supply Company, Qingdao 266002, Chin)
出处
《山东电力技术》
2018年第1期29-32,46,共5页
Shandong Electric Power
关键词
景观式变电站
面对面布置
规划设计
landscape substation
face to face arrangement
planning design