摘要
针对反应堆紧急停堆子系统,将故障模式影响分析(FMEA)、故障树分析(FTA)、系统理论的过程分析(STPA)3种独立的基本分析方法进行组合,形成仪表控制系统设计阶段的失效和故障基本项覆盖统计表格。STPA方法能够很好地弥补了FMEA和FTA方法的不足。同时,在仪控系统的设计阶段,STPA方法非常适合发现反应堆紧急停堆子系统涉及的软件类、系统交互以及通信类的故障和安全问题。
For the reactor scram subsystem, the failure and fault coverage statistics form for the instrument control system design phase is deduced by the combined use of three independent basic analysis methods FMEA, FTA, and STPA. STPA method can effectively make up for the inadequacy of FMEA and FTA method. At the same time, in the instrument control system design phase, STPA method is very suitable for finding the fault and safety issues in software, system interaction and communication for the reactor scram subsystems.
作者
刘华
韩文兴
阳小华
陈智
刘朝晖
Liu Hua;Han Wenxing;Yang Xiaohua;Chen Zhi;Liu Zhaohui(School of Electrical Engineering, University of South China, Hengyang, Hunan, 421001, China;Nuclear Power Institute of CHINA, Chengdu, 610041 China;School of Computer Science and Engineering, University of South China, Hengyang, Hunan, 421001, China)
出处
《核动力工程》
EI
CAS
CSCD
北大核心
2018年第3期156-161,共6页
Nuclear Power Engineering
基金
反应堆系统设计技术重点实验室开放基金
中核集团高可信计算学科重点实验室共同资助(HT-LW-02-2014005)
关键词
多方法融合
反应堆紧急停堆
安全性分析
Multiple method fusion
Reactor scram subsystem
Safety analysis