沉管碎石基床清淤新方法 被引量:2

New method of removing silt from gravel bed of sinking pipe
下载PDF
导出
摘要 结合现有的清淤设备和方法,利用漂浮式母船与水下清淤系统相结合的方式,根据沉管基床垄顶和垄沟回淤情况,采用环保疏浚中成熟应用的螺旋刀头将沉积淤泥扰动为泥水混合物,冲刷系统再次冲刷垄顶和垄沟残余淤泥扰动为泥水混合物。清淤泵提供动力,通过已成熟应用在港珠澳沉管碎石基床面的清淤系统吸头将泥水混合物吸走,实现基床垄顶和垄沟清淤,达到预期的清淤效果,实现对沉管基床的清淤施工。该方法可进一步为构筑物水下基床的清淤施工提供借鉴。 Combined with the existing desilting equipment and methods, using the combination of floating mother ship and underwater silt cleaning system, according to the condition of siltation in the top of bed and furrow of sinking pipe, the silt deposit is disturbed into muddy water mixture by the spiral knife head which is used in environmental protection dredging, and the residual silt on the top of the ridge and the residual silt in the furrow is disturbed into the mudwater mixture by the scouring system again. The desilting pump provides the power to suck the mud-water mixture away from the mud-water mixture through the suction head of the desilting system used in Hongkong-Zhuhai-Macao Bridge sinking tube gravel base surface, so as to realize the silt clearing at the top of the base bed and the furrow, achieve the expected silt clearing effect. The desilting construction of sinking pipe bed can be realized, and the method can further provide references for foundation bed desilting construction of underwater structure.
作者 张乃受 冯海暴 ZHANG Nai-shou;FENG Hai-bao(CCCC First Harbor Engineering Co.,Ltd.,Tianjin 300461,China)
出处 《中国港湾建设》 2018年第7期52-56,共5页 China Harbour Engineering
基金 国家重点研发计划(2017YFC0805305)
关键词 沉管隧道 碎石基床 清淤施工 immersed tunnel stone bed dredging construction
  • 相关文献

参考文献6

二级参考文献15

共引文献42

同被引文献12

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部