摘要 青岛地铁2号线枣山路车站采用大拱脚拱盖法施工揭示的地质情况与原地质勘探结果不符,原支护体系无法满足地表沉降、拱顶沉降及主体结构受力的要求,因此提出含软弱夹层地铁车站拱盖-锚索-注浆组合支护体系。运用数值分析及稳定性增量的方法研究了注浆加固层厚度、锚索位置及条数、锚索初始预应力对支护效果的影响,确定了该组合支护体系最优的支护参数:注浆加固层厚度为3 m,拱脚及下断面中部各打设1根预应力为200 k N的锚索。 Zaoshan Road station construction of Qingdao Metro Line 2 with large arch foot arch cover method showed that geological conditions is inconsistent with the original geological exploration results,the original support system cannot meet the requirements of ground subsidence,vault subsidence and main structure stress,and the arch cover-anchor cable-grouting combined support system of subway station with weak intercalation was proposed.Numerical analysis and stability increment method was used to study the influence of grouting reinforcement layer thickness,anchor cable location and number, initial prestress of anchor cable on support effect,t he optimum support parameters of this combined support system were determined, in which the thickness of the grouting reinforcement layer is 3 m,and an anchor cable with prestress of 200 kN should be placed in the anchor foot and the middle of the lower section respectively.
作者 袁国栋 王渭明 YUAN Guodong;WANG Weiming(Shandong Provincial Key Laboratory of Civil Engineering Disaster Prevention,Shandong University of Science and Technology,Qingdao Shandong 266590,China)
出处 《铁道建筑》 北大核心 2018年第9期58-62,共5页 Railway Engineering
基金 国家自然科学基金(41472280)
关键词 地铁 拱盖-锚索-注浆组合支护体系 数值计算 支护参数优化 拱盖法施工 软弱夹层 Subway Arch cover-anchor cable-grouting combined support system Numerical calculation Supportparameter optimization Arch cover method construction Weak intercalation
  • 相关文献

参考文献10

二级参考文献95

共引文献204

同被引文献4

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部