摘要
智能变电站母线改扩建工程目前多采用变电站全停的改造模式,对电网运行影响较大。以某220 k V智能变电站母线和主变扩建工程为例,分析了该智能变电站母线和主变间隔扩建对全站二次设备的影响和调试需求,在一次设备停电影响最小的前提下,提出了扩建工程继电保护改造技术方案、施工方案及各环节的安全措施,避免了因改扩建工程对地区电网供电造成严重影响。
At present bus reorganization and expansion project of smart substation involves more intervals,so that all stop mode of substation is mostly used to avoid the risk of operation in the reorganization process,which has a great effect on grid operation.Taking certain220kV smart substation bus and the main transformer extension project for example,this paper analyzed the impacts of smart substation bus and main transformer interval extension on the whole station secondary equipment and the debugging requirement.Under the premise of minimizing the interruption of the running primary equipment,this paper proposed the expansion project relay protection reconstruction technology scheme,the construction scheme and the safety precautions of each link to avoid the strong impacts caused by the reconstruction and extension project on the regional grid power supply.
作者
邵庆祝
赵创业
谢民
王海港
SHAO Qing-zhu;ZHAO Chuang-ye;XIE Min;WANG Hai-gang(State Grid Anhui Electric Power Company, Hefei 230022, China;State Grid Huaibei Electric Power Company, Huaibei 235009, China)
出处
《电工电气》
2017年第12期37-41,共5页
Electrotechnics Electric
关键词
智能变电站
改扩建工程
继电保护
安全措施
smart substation
reorganization and extension project
relay protection
safety precautions