大跨度拱桥斜拉扣挂体系施工阶段分析 被引量:3

Analysis on Construction Stages of Cable Stayed Fastening System of Large-span Arch Bridge
下载PDF
导出
摘要 斜拉扣挂法属于拱桥无支架缆索吊装法的一种,其基本思路是在加工厂制作拱肋块段,现场分段起吊至设计位置,采用斜拉索结构承载拱肋自重、控制拱肋线形,最终完成拱肋合龙。文章依托某主跨507m的大跨度钢管混凝土拱桥工程实例,介绍了斜拉扣挂法施工阶段索力计算分析方法,提出了扣塔受力计算分析的优化算法,为类似工程提供参考。 The cable-stayed fastening method belongs to a kind of non-bracket cable hoisting method of arch bridge,its basic idea is to manufacture the arch rib block in the processing plant,hoist it in segments to the designed field position,use the stayed cable structure to bear the weight of arch rib and control the arch rib linearity,then eventually complete the arch rib closure.Based on the project example of large-span CFST arch bridge with a main span of 507 m,this article introduced the cable force calculation and analysis method at the construction stage by cable-stayed fastening method,and proposed the optimization algorithm for the calculation analysis of fastening-tower force,which can provide references for similar projects.
作者 李哲 孙克强 LI Zhe;SUN Ke-qiang(CCCC Second Highway Engineering Co.,Ltd.,Xi an,Shaanxi,710065)
出处 《西部交通科技》 2018年第1期150-153,157,共5页 Western China Communications Science & Technology
关键词 大跨度拱桥 斜拉扣挂 索力 扣塔 施工阶段 Large-span arch bridge Cable-stayed fastening Cable force Fastening-tower Construc-tion stage
  • 相关文献

参考文献4

二级参考文献16

共引文献50

同被引文献18

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部